Regional Park, LLC

OwnerRegional Park Limited Partnership
Client Regional Park Limited Partnership
Location Sacramento, CA
Scope Of Work 901 kw
Schedule 2 Months
EngineerSolar City

Project Detail

Collins Electrical Company, Inc. is pleased to have partnered together with Solar City to provide a Balance of System installation for the Regional Park PV project located in Sacramento, CA. The 901 kw carport photovoltaic design was comprised of a Bi-Polar system consisting of an Advanced Energy 500 kw inverter and a 333 kw inverter, 480 v distribution gear and customer interconnection. The project commenced on 11/03/2011 and was completed on 12/29/2011.