Sacramento Based Company

OwnerSacramento Based Company
Client Siemens Building Technologies
Location Sacramento, CA
Scope Of Work 1.16 kw
Schedule 2 Months
EngineerBlue Oak Energy

Project Detail

Collins Electrical Company, Inc. was proud to participate in the 1.16 MW solar installations in Sacramento, CA. The project consisted of 2,744 Sharp 235 kw panels for a carport system size of 644,840 kw and 2,174 Sharp 235 kw panels for the roof mount system size of 510,890 kw. The project commenced on 5/15/2010 and was completed on 7/15/2010, The scope of work was comprised of a complete Balance of System for the carport arrays, installation of distribution gear, inverters, and Customer Interconnection.