Davis Joint USD

OwnerDavis Joint USD
Client Davis Joint USD
Location Davis, CA
Scope Of Work 585 Kw
Schedule 45 Days
EngineerBlymyer Engineers

Project Detail

Collins Electrical Company, Inc. was proud to participate in the 585 KW solar installations at the Davis Sr. High School, Davis, CA location. The project consisted of 2,268 Suniva 260 watt panels for a carport system size of 590 KW. The project commenced on 5/15/2021 and was completed before the new fall semester on 6/30/2012, The scope of work was comprised of a complete Balance of System for the carport arrays, horizontal boring of AC run, installation of distribution gear, inverters, and Customer Interconnection.